The Collins Class Submarine Story

Home > Other > The Collins Class Submarine Story > Page 19
The Collins Class Submarine Story Page 19

by Peter Yule


  the government procurement organisation. Gunnar Öhlund, now

  Kockums’ technical director, says that: ‘Kockums was used to a

  smooth process with the customer based on trust and a long work-

  ing relationship – you agree and shake hands and that is that.’

  The problems that inevitably arose in designing and building sub-

  marines were resolved by the joint efforts of the three organisa-

  tions, which were closely linked by ties of friendship and many

  years of working closely together.

  Chicago Bridge & Iron (CBI) was one of the world’s lead-

  ing engineering contractors, working each year on hundreds of

  projects around the world for a wide variety of customers. The

  company specialised in lump-sum ‘turnkey’ projects in the oil, gas,

  petrochemical and mining industries, and had submarine experi-

  ence in fabricating hull sections for American submarines. Ross

  Milton, who joined CBI in 1971, saw its ‘modus operandi’ as

  ‘moving onto construction sites and building up to say 400 peo-

  ple, constructing a section of an oil refinery to a schedule and a

  cost and then moving out’.

  Wormald in the 1980s was one of Australia’s largest diversified

  engineering conglomerates, with interests in many areas including

  electronics and fibre optics. Its managing director, Geoff Davis,

  was well-connected in Australian business and politics and the

  company did much to organise the submarine project’s Australian

  sub-contractors.

  The fourth original partner, the Australian Industries Develop-

  ment Corporation, was initially a largely silent partner, concerned

  primarily with the financial aspects of the project.

  These vastly differing backgrounds made it almost inevitable

  that there would be difficulties in setting up a harmonious joint

  venture. One interesting reflection from the Swedish side is that

  S E T T I N G T O W O R K 1 9 8 7 – 8 9

  121

  they were surprised at the rigid hierarchies of the Australian

  and American companies. Roger Sprimont says that he found

  Australians to be genuinely friendly and easygoing, but he found

  hierarchy more important in the corporate world than it was in

  Sweden. Like the other Swedes he was amazed that the first chart

  of the management structure of ASC showed what model of com-

  pany car each level of management could have.

  Despite these differences, there was a good corporate spirit

  as people from the four companies worked together with new

  recruits to get the project moving. Looking back on the early days

  of the project, Ross Milton recalls:

  We had a lot of esprit de corps in those days. They were

  exciting times. It was the biggest thing that ever happened in

  Kockums’ world and they were keen as mustard to do a good

  job. We all were. It was easily the biggest project any of us

  had experienced.

  When the contract was signed, the Australian Submarine Cor-

  poration was little more than a name and a letterhead, with no

  employees, and operating from offices borrowed from Wormald

  in the Sydney suburb of Brookvale. Yet this company was prime

  contractor for a multi-billion dollar new submarine project, com-

  mitted to building a new submarine design on a site that was little

  more than a polluted swamp, using sub-contractors from 10 coun-

  tries including many Australian companies that had no previous

  experience of military work.

  The members of ASC’s board played an active and energetic

  role in the early phases of the company’s operations, particularly

  until the senior management positions were filled. Geoff Davis

  was the chairman and he often smoothed over potential disagree-

  ments between Kockums and CBI. Unfortunately for the project

  he was forced to resign as chairman in October 1987, following a

  change in the ownership of Wormald. He was succeeded by Roger

  Sprimont, the leader of the Kockums bid. Sprimont provided ASC

  with charismatic and inspiring leadership, although naturally he

  did not have the same depth of contacts in Australian business and

  politics as Geoff Davis. Sprimont’s departure from the project in

  November 1989 when he was appointed to a senior position with

  the Swedish Hagglunds group was a major blow for the project.

  The early loss of two outstanding leaders had a serious impact on

  122

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  the project and they were never fully replaced. The later history

  of the project would have been very different if one or both had

  remained involved.

  The schedule for building the submarines was always seen as

  being ambitious, and ASC had to plan rapidly to mobilise peo-

  ple and resources to get the project moving. Olle Holmdahl of

  Kockums recalls that CBI played a crucial role at this stage:

  It was very important for ASC to have CBI on board for the

  early years. They had submarine expertise . . . they knew steel

  construction, and they were experienced project managers.

  They knew how to set up projects in new countries. Kockums

  did not have the skills, people or experience to do this. So it

  was CBI people who did all of the work in setting up the

  project.1

  CBI, working with Bath Iron Works, a leading American naval

  shipbuilder, set up ASC’s planning systems and designed the facil-

  ities to match the proposed production techniques and the work

  flow. Ross Milton recalls that CBI studied the way Kockums built

  submarines and adopted some of their methods, but in many cases

  they thought their own methods would be more efficient.

  While Kockums appreciated CBI’s ability to get a project

  moving quickly, there were some conflicts over the systems they

  adopted. Some of the Swedes thought that CBI ‘planned in too

  much detail – they were planning way ahead for the delivery of

  the smallest item even before they were designed [and] this caused

  some confusion later – CBI planned minutely but without suffi-

  cient knowledge of submarine systems’.2 Paul-E P ˚alsson, the pres-

  ident of Kockums, felt that ASC should have used the planning

  and procurement controls that Kockums was familiar with, and

  that the Kockums people with ASC accepted CBI’s methods too

  early and too easily. On the other hand, CBI was concerned that

  Kockums was not moving quickly enough to keep to the schedule

  and not providing information in time to enable ASC and CBI to

  meet their contractual obligations.

  One of the most urgent tasks for ASC was to assemble the

  workforce needed to build the submarines. The core of the new

  management was seconded from ASC’s shareholders, with Ray

  Hill of CBI becoming the first general manager, and other senior

  positions being filled by Jeff Rubython and Roger Mansell of

  S E T T I N G T O W O R K 1 9 8 7 – 8 9

  123

  Wormald, Ross Milton, Jim Berger, Jim Muth and Graeme Ching

  of CBI and Bath Ironworks, and John O’Neill and Olle Holmdahl

  of Kockums. However, most
of these people left the project or

  returned to their parent companies when CBI and Wormald were

  bought out and the shareholding arrangements in ASC changed.

  There was a major recruiting program for staff at all levels.

  The first chief executive, Don Williams, began work on 1 January

  1988. A civil engineer with a background in railways and a doc-

  torate from Imperial College in London, he came to prominence

  for his work on rebuilding Melbourne’s West Gate bridge. Before

  coming to ASC he was general manager of Australian National

  Railways.

  Although views on Williams have been coloured by later

  events, there is general agreement that he was ‘a great influence

  and a good one for the early part of the project’.3 He was intelli-

  gent, a good public speaker, politically astute and had many con-

  tacts in Canberra. He was somewhat aloof from his staff, but

  drove the project forward with enormous energy. Oscar Hughes

  saw him as ‘a visionary in the context of doing things for Australia

  [who] fought hard to make ASC a success’.

  From late 1987 a large number of engineers and other profes-

  sionals joined ASC. Martin Edwards had worked for DSTO at

  Salisbury, north of Adelaide, for eight years before joining ASC in

  January 1988. There were two intakes that month of people who

  were to be seconded to Sweden, to work either for Kockums or at

  the ASC project office in Malm ö. After a brief induction program

  about 24 ASC staff were sent off to mid-winter in Sweden. Most

  of them were young, with the average age being in the mid-20s.

  Edwards worked with the design team at Kockums for more than

  two years before returning to Adelaide.

  Jack Atkinson had worked for the Department of Defence as

  a software engineer for 14 years before joining ASC in 1988. He

  came as a senior systems engineer to work on the weapons system

  integration. Software quickly came to be seen as one of the main

  risk areas of the project and ASC built up a far greater capabil-

  ity in the area than originally planned. Ron Dicker, who had led

  the Signaal combat system bid, recalls that he was on holiday in

  Italy when Roger Sprimont called. He was concerned about the

  combat system contract and needed experience and knowledge to

  monitor Rockwell and protect Kockums’ interests. Dicker set up

  124

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  a weapons system department in ASC to manage the weapons sys-

  tem sub-contracts and their integration with the combat system

  and the integration of the combat system into the submarine, and

  to monitor Rockwell’s progress.

  As the project advanced ASC began to employ people with

  production expertise. Many brought their knowledge of subma-

  rine mechanical engineering from the Oberon refitting program at

  Cockatoo Island. Among them were Charlie Yandell, who became

  production manager, Robert Lemonius, to be submarine manager,

  and Alan Saunders.

  Another source of expertise was the United Kingdom. The Aus-

  tralian project appeared to offer more secure employment than

  Britain’s uncertain submarine building program. Doug Callow

  had been with Vickers for 26 years and was project manager

  for the Trident nuclear ballistic missile submarines when Don

  Williams recruited him in 1992. Jock Thornton was an ex-Royal

  Navy nuclear submarine engineer, while Charlie Yandell had

  been production manager at Scotts of Greenock before going to

  Cockatoo Island.

  Many engineers came to ASC in the late 1980s immediately

  after graduating. Simon Ridgway was employed straight from uni-

  versity and spent his first year working in a small group headed

  by G öran Christensson from Kockums, developing the program

  for outfitting the submarines.

  If recruiting professional staff with submarine experience was

  difficult, it was even harder to build a skilled workforce. Although

  manufacturing industries around Adelaide had been particularly

  hard hit by Australia’s worst recession since the 1930s and many

  were attracted by the security of a large military program, the

  skills required were distinctly higher than in most other areas.

  Robert Lemonius recalls: ‘We’d take a very good high pressure

  vessel welder who’d worked on pipelines and engineering projects

  and things like that and in some cases spend anywhere between

  eight and 12 weeks on developing those skills before they would

  be allowed to actually undertake production welding.’ ASC gave

  a great deal of attention to training its workers, bringing them

  up to the required standard and teaching them new processes and

  procedures.

  One of the most urgent tasks for ASC was to let hundreds of

  sub-contracts. Contractually, at least 70 per cent of the cost of the

  S E T T I N G T O W O R K 1 9 8 7 – 8 9

  125

  submarines had to be spent in Australia. This meant either that

  foreign sub-contractors had to establish subsidiaries in Australia

  or that the sub-contracts had to be given to Australian compa-

  nies. Contracts manager Roger Mansell succeeded in negotiating

  the required Australian content even though ‘the major overseas

  suppliers were keen to retain as much work as possible for their

  own people, and they were reluctant to share commercial infor-

  mation with potential rivals’.4

  Tore Svensson of Kockums recalls that he visited a number of

  companies in Australia with no experience in defence that had

  built their expertise from scratch and developed good products.

  Sometimes it was decided that work could not be done in Australia

  and had to be done in Europe, especially for the first submarine,

  but Kockums and ASC assisted many local companies to raise

  their quality standards, to their long-term benefit.5

  ASC shareholders, with the exception of AIDC, all took on

  major sub-contracts. Kockums had contracts to design the sub-

  marines and to build two hull sections and two interior deck

  assemblies for the first submarine. CBI was to fabricate the plate,

  frames and bulkheads, and Wormald was contracted to design

  and project manage the new yard at Osborne and provide the

  submarines’ fire-fighting system, and had several major contracts

  related to the ship control system. Geoff Davis of Wormald notes

  that ‘the shareholder agreement allowed that each shareholder

  who undertook work . . . was entitled to a minimum margin of

  10 per cent’. For Wormald the opportunity was available to secure

  contracts worth over $600 million, but many of these were not

  followed up after Geoff Davis’s resignation.

  The largest sub-contract was with Rockwell for the combat sys-

  tem. This was far from a normal sub-contract and the relationship

  between ASC and Rockwell was never a normal contractor/sub-

  contractor relationship. The combat system contract and the sub-

  marine contract had been negotiated parallel to but completely

  separate of each other. Security arrangements prevented ASC from
/>
  viewing the combat system specifications, so it had to approve the

  sub-contract and establish the submarine–combat system interface

  document with Rockwell sight unseen. After three months nego-

  tiations ASC reluctantly accepted the sub-contract. Ron Dicker

  says: ‘Rockwell had of course no incentive to change even a

  comma in the contract they had negotiated between themselves

  126

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  and the Commonwealth’ so the ‘process resulted in a “special”

  relationship between Rockwell and the Commonwealth to the

  detriment of ASC’s ability to pro-actively manage the combat sys-

  tem contract’.

  Most of the other major sub-contracts had been foreshad-

  owed in the project definition study phase: diesel engines from

  Hedemora, weapons discharge system from Strachan & Henshaw,

  propulsion motors and generators from Jeumont-Schneider, ship

  management systems from Saab Instruments, and masts from Riva

  Calzoni. All these firms had further large sub-contracts with Aus-

  tralian companies.

  The decision to award the contract for diesel engines to

  Hedemora was later strongly criticised, and even at the time

  it was the subject of debate. The two contenders for the con-

  tract were Hedemora of Sweden, a small private company, and

  MTU [Motoren- und Turbinen-Union Friedrichshafen GmbH] of

  Germany, now part of the Tognum group. Kockums’ design stud-

  ies showed that the submarine could be considerably shorter with

  Hedemora engines. The required power could be delivered by

  three Hedemoras arranged abreast, but would need two banks

  of two MTU engines. Greg Stuart was convinced that there were

  technical advantages in the Hedemora engine. He recalls that:

  I had extensive discussions with MTU’s chief designer, Herr

  Dr Jost, who acknowledged that MTU was behind

  Hedemora and at that time could not offer a low risk

  turbocharged submarine diesel to meet the RAN’s depth and

  sea state requirements . . . Hedemora on the other hand was

  able to demonstrate, from memory, a 12-cylinder version of

  the Collins diesel under simulated variable snort conditions

  based on the RAN supplied sea state profile. The diesel

  operated without a problem for the trial duration.6

  The situation became complicated in 1987 when the Swedish navy

  switched from Hedemoras to MTU engines for the new Gotland

 

‹ Prev