The Collins Class Submarine Story

Home > Other > The Collins Class Submarine Story > Page 21
The Collins Class Submarine Story Page 21

by Peter Yule


  submarine and Kockums had not designed such a big

  submarine before – but neither had anyone else. Size in itself

  was not the difficulty, but as a submarine gets bigger there

  are more systems and more complexity, which means more

  specs, more drawings, and more work.

  Further, almost all of the equipment that went into the submarines

  was specific to purpose and very little ‘off-the-shelf’ equipment

  134

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  was used.3 Kockums, even where it did not design the equipment

  itself, was responsible for supervising the sub-contractor and for

  integration. The company had 25 000 drawings to do, as well as

  drawing up parts lists and preparing the procedures for production

  and testing.

  Kockums’ partners in ASC felt that the biggest risk of the

  project was the design process, and feared that this might be

  beyond Kockums. Although Kockums’ risk management evalu-

  ation convinced the partners that the potential problems could be

  successfully overcome, most people involved believe that Kock-

  ums underestimated the size of the design task. Mark Gairey, a

  naval architect with the Australian navy team in Malm ö, says that:

  Kockums didn’t think the design effort would be more than

  20 per cent more than on the Swedish submarines, but it

  turned out to be about double. While doing Collins they were

  building one class of Swedish submarines and in detailed

  design of the next one and doing detailed research for the one

  after that. And while they were doing this they were finding

  our project took more work than they expected. To do the

  work on Collins as well took more resources than they had

  and they are not the sort of resources you can just go out and

  buy. They robbed Peter to pay Paul to fix the crises as they

  emerged.

  While those at Kockums would think this is an overstatement,

  members of their design team agreed that the design process took

  longer than they expected, largely because they were dealing with

  a new customer and they had to get used to responding to new

  questions and more formal ways of working. An additional com-

  plication was the need to rely on others. Gunnar Öhlund pointed

  out that:

  ASC was responsible for procurement and Kockums relied

  on information from suppliers to be delivered on time and of

  high quality. Kockums was slowed by others being slow – the

  structure of the organisation might not have been the best.

  Vendor furnished information was a real challenge. Kockums

  should have been stronger explaining to ASC the need to

  deliver information in a timely manner and this led to

  problems settling details for the design.

  D E S I G N I N G T H E C O L L I N S C L A S S

  135

  About 18 Australian engineers and designers joined ASC and were

  sent to work with Kockums in Malm ö. The intention was that

  they would work closely with the Kockums design team to learn

  skills and to equip them for management roles during the con-

  struction phase. Martin Edwards was one of this group, and he

  recalls that the Kockums people were obviously fairly cautious to

  begin with and would allocate one or two very small or simple

  design tasks or engineering activities. They would delegate more

  responsibility after the Australians had demonstrated knowledge

  and ability. His impression was that after about four to six

  months a number of ASC people were taking on more significant

  roles within the design activity but being mentored by Kockums

  designers:

  I worked on designing aft control surface arrangements,

  integration of the masts, garbage ejector and compactors,

  main propulsion motor installation, some of the more

  significant mechanical tasks, their integration into the

  submarine.

  Edwards found that in designing Collins, Kockums used the prin-

  ciples from the V ästerg ötland and other earlier Swedish sub-

  marines, but most of the detailed design was completely new,

  partly because of the great difference in size and partly because

  much of the equipment specified or chosen for Collins was new.

  So, while the hull outline was virtually indistinguishable from the

  V ästerg ötland and elements of previous designs could be used for

  mounting equipment and so on, most of the detailed design work

  had to be done from scratch. For example, ‘the masts were com-

  pletely new to the Swedes and it [was] an Italian design that was

  used, so they had to be designed and integrated from first prin-

  ciples’. The Swedes aimed to build on previous work but it was

  often found that only minor details could be used.

  As well as the ASC engineers and designers working with Kock-

  ums, there was also a navy team of about 20 people, headed by

  Captain Rick Canham, based in Malm ö to supervise the design

  work, clarify the navy’s requirements and report back to the

  project office in Canberra. Mark Gairey was given the title of

  ‘senior technical representative, Europe’ and recalls that the team

  was ‘on the ground in Sweden before ASC’. He felt that Kockums

  136

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  had a pretty good idea what they had to do. They’d been

  designing and building submarines for 70 odd years.

  However, one of the problems we encountered was that they

  kept looking at things in a Swedish frame of reference. There

  were some interesting and prolonged discussions which

  ended up with us saying: ‘That’s fine but we simply can’t live

  with that solution in an open ocean environment. It’s all very

  fine for you guys where, if it goes wrong, you’re sitting in a

  little puddle of water and can fix it, but we can’t.’ We had

  several discussions of that type on and off because ultimately

  we had a specification but there were still gaps in it.

  When the navy team and Kockums could not agree on an issue,

  they would report back to the project office in Canberra outlining

  the problem and saying what they thought should be done. It then

  became a contractual matter back in Australia between the project

  office and ASC.

  To help ASC achieve 70 per cent Australian content Kock-

  ums set up a design office in Adelaide. This office was manned

  by Swedes and Australians, with most of the Australians who had

  been working in Malm ö returning to Adelaide by 1990 or 1991. At

  its peak this office had about 40 Australian and 20 Swedish staff,

  headed first by Jan Hansson and later by Martin Edwards. The

  fact that an Australian took over from a Swede was in itself one of

  many vindications of the project’s aspiration to develop Australian

  skills. As design manager at ASC Edwards was responsible for all

  the detailed design groups and some of the engineering support.

  The design groups covered hull design, mechanical design, out-

  fitting design, weapons handling, electrical design and electrical

  installation, fo
cusing on finalising the detailed design components

  and supporting production.

  With design work proceeding on opposite sides of the world,

  communication between the design offices was vital. There were

  many issues that required discussion and debate between Adelaide

  and Malm ö and, with e-mail only coming into common use about

  halfway through the project, they had to be resolved by fax or

  telephone discussion. It was vital that both design offices have the

  same drawings and documentation, so a dedicated link was set up

  for daily transfers. Drawings done in Malm ö would be encrypted

  and sent by satellite, navy to navy, to Adelaide.

  D E S I G N I N G T H E C O L L I N S C L A S S

  137

  Gairey recalls that the Australian navy team at Malm ö had

  many debates with Kockums’ designers, but he does not recall

  any issues that could not be resolved. Significantly, he says: ‘the

  problems that arose later caught us by surprise. They were things

  we didn’t expect. Whether we should have been better prepared

  is a good question.’

  During the controversies that raged around the submarine

  project in the late 1990s, many aspects of the design were ques-

  tioned. Hindsight is a wonderful thing, but how were these issues

  looked at by the Kockums designers, their Australian protégés,

  and the project team in the late 1980s?

  The shape of Australia’s new submarines was taken directly

  from that of the V ästerg ötland. Looked at in profile the two classes

  are almost identical. The hull shape of the V ästerg ötland, as with

  all Swedish submarines, was developed jointly by Kockums, the

  Swedish navy and SSPA Maritime Consulting AB (now SSPA Swe-

  den AB) in G öteborg. Hans Peder Loid, who was managing direc-

  tor of SSPA when the V ästerg ötland was designed, recalls that all

  the design activity for Swedish submarines was between Kockums,

  FMV and SSPA and no changes would take place unless all three

  were united. It was never a rigid supplier/customer relationship.

  If there was anything not completely necessary on the hull, SSPA

  would reject it, as a tiny protrusion or an extra hull penetration

  could make a big difference to noise levels.

  Tank testing of models for new classes was done as a normal

  procedure, and he was involved with the tests of the V ästerg ötland

  and of the Australian design up to the signing of the final contract.

  At that stage the testing done at SSPA had revealed no problems.

  Loid emphasised that the shape of the Australian submarine at

  that time was the same as the V ästerg ötland except bigger, so

  there was no reason why its hydrodynamic signature would not

  be identical to a Swedish submarine unless things were added to

  it later during the design or construction.

  However, the hull design of the Collins class did alter from

  that put forward at the end of the project definition study. The

  submarine became even bigger – although this in itself should not

  have affected the water flow characteristics – and other changes

  were made that had the potential to affect the submarine’s noise

  level. For example, it was discovered that the sonar suppliers,

  Thomson-CSF, had underestimated the required clear angles for

  138

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  the sonar and the design had to be stretched one metre forward

  to accommodate the sonar accessories and one metre aft to retain

  balance, while the sonar bow dome shape had to be drastically

  re-designed. The modified design was not tank tested, mainly due

  to disagreement about who should bear the cost of building a new

  model to test.4

  Mark Gairey says that in retrospect both the Swedes and

  the Australians were looking at potential noise problems from

  the perspective of the Oberons, where the noise came mainly

  from the machinery. Machinery noise was overcome in Swedish-

  designed submarines by construction using resilient platforms

  with rubber isolation elements. This link between the design and

  the modular construction techniques had been one of the great

  attractions of the Swedish bid. However, while concentrating

  on eliminating machinery noise, neither the Swedes nor the

  Australians anticipated problems with hydrodynamic noise.

  Gairey suggests that:

  In part it was our inexperience and in part because of the

  way the Swedes operated their submarines, they had never

  seen these problems. I’m sure that their submarines would

  have the same problems if operated by our people, but they

  didn’t so it was a surprise for them as well.

  The Swedes operated at very short range. They’re very

  much a coastal defence force . . . They went four hours out of

  harbour and sat there. They weren’t running at any sort of

  speed for any sort of distance . . . Whereas we had big

  distances to transit to an operating area and we wanted to

  transit as quickly as we could, while remaining undetected. It

  was a completely new set of requirements . . . Maybe they

  could have done more model testing but they were looking at

  Collins through a Swedish frame of reference. They didn’t do

  with their submarines what we did so they didn’t have the

  problems and they didn’t anticipate that we would. They

  didn’t realise our operating environment was so different. In

  retrospect they should have done more testing but at the time

  it seemed that what they did was fine. We were totally

  surprised by the problems we had and the Swedes were just

  as surprised.

  Critics of the Collins class submarines have argued: ‘The shape of

  the submarines in the water was a disaster because of the insistence

  D E S I G N I N G T H E C O L L I N S C L A S S

  139

  on six torpedo tubes across the front so that the submarine has a

  front like a circumcised dick.’5 The designers agree that the snub

  nose of the Collins class creates turbulence when on the surface,

  but the submarine spends most of its time submerged, where the

  bow shape works well, although the area aft of the bow where

  the sonar dome joins the casing was later found to be a source of

  turbulence.

  Gunnar Öhlund, who worked on the bow design, says the

  arrangement of tubes side by side provides compact weapons stor-

  age and enables fully automated handling and loading. He argues

  that this had no consequences for the hull shape and there are ben-

  efits for firing in keeping the torpedo tubes below the boat’s centre

  line. This design has worked well with the Swedish submarines.6

  SSPA in G öteborg was closely involved in the design of pro-

  pellers for Swedish submarines and also for the new Australian

  submarine. In the 1980s the Swedish submarines had a problem

  with a ‘singing’ propeller but a lot of research and then a few small

  marks on the propellers were enough to fix this. However, cavita-

  tion was always the main concern with Swedish propellers. SSPA

  developed a computer program
that prevented the crew operating

  the submarines in a way that caused cavitation and this essentially

  solved the problem on Swedish submarines before the Australian

  project, although it could emerge if the design was changed or the

  propeller was poorly manufactured.

  Generally the requirements for the submarines were stated in

  performance terms, but in some areas design requirements were

  specified. One of these was that the propellers be made from

  Sonoston or a similar highly damped alloy because it had been

  used in recent American submarine propellers.7 Unfortunately the

  Australian navy did not known that the alloy was liable to crack

  and had been abandoned by the Americans. Mark Gairey com-

  ments that: ‘In hindsight, this was a mistake and we should have

  concentrated on the “no cavitation” requirement and left it to the

  designer to solve.’

  A controversial aspect of the design of the new submarines

  was the decision to have flat rather than round bulkheads in the

  bow and stern sections. The Swedish navy had used both round

  and flat bulkheads and decided that either worked. Kockums saw

  flat bulkheads as robust, saving space and allowing the torpedo

  tubes to be positioned identically. They have been used in Swedish

  submarines since the Sea Serpent class of the 1960s, which are still

  140

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  in service with the Singapore navy, indicating that hulls built with

  flat bulkheads can have a very long life.8

  Some significant design changes were initiated by the Aus-

  tralian navy team at Malm ö which, while beneficial, often caused

  contractual difficulties. One such change occurred with the air

  purification system. Greg Stuart, the senior engineer with the

  project, recalls that the Swedish system in the original design

  was ‘heavy and inefficient’. Stuart contacted Wellman Processing

  Engineering of Birmingham, England, which owned the technol-

  ogy used for air purification on some British and American sub-

  marines. Working with Wellman, Stuart calculated that changing

  the air purification system could save length and weight on the

  submarines, and he developed a proposal for a ‘mini-scrubber’

  to remove carbon dioxide and other acid gases. The first unit

  was called ‘Kylie’, ‘the little Aussie scrubber’, and the second was

 

‹ Prev