The Collins Class Submarine Story

Home > Other > The Collins Class Submarine Story > Page 42
The Collins Class Submarine Story Page 42

by Peter Yule


  led to poor morale throughout the project. The capability team

  hired Brisbane public relations consultants the Philips Group,

  whose principal, Stephanie Paul, became an integral part of the

  submarine ‘get-well’ program. She saw the submarine project as a

  crisis situation, with urgent action needed to break the downward

  spiral.

  Paul drew up a comprehensive public relations plan based

  on responding to the criticisms and repairing the damage to the

  submarines’ reputation. They had to acknowledge the faults and

  establish the credibility of the capability team with the media.

  Previously there had been an information void on the project and

  there had been no effective response to the extreme and sensa-

  tionalist stories in the media, but gradually the Philips Group’s

  strategy built up trust by presenting the media with factual and

  verifiable material. Stephanie Paul emphasises that she did not see

  the work as ‘selling something’, but as carrying out an essential

  part in getting the project back on track.

  290

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  Briggs found that morale at ASC was a serious problem: the

  workforce was reeling from the barrage of bad publicity and

  apprehensive that the project would be shut down. He tried to

  convince the workers that the problems were not their fault and

  they were part of the solution.

  Kockums he felt to be a more serious obstacle. The fast-track

  timetable relied on getting rapid approval from Kockums, the

  design authority, for the design changes. However, approval was

  always slow, possibly through an unwillingness to accept that

  changes were necessary, although Briggs felt it was due to a decline

  in the company’s design capability. In the end most of the design

  changes were done in Australia and only approved retrospectively

  by Kockums.

  ASC responded warily to the capability team. Peter Briggs char-

  acterises Hans Ohff’s reaction as being: ‘What are you here for?

  There’s nothing wrong with the submarines.’ In Briggs’ view ASC

  had not looked beyond the delivery of six submarines to see that

  there should be 20 years work for the company in looking after

  the submarines, but a better relationship with the customer was

  essential before this could happen.

  Hans Ohff’s views were very different. He saw the whole

  McIntosh-Prescott report and the establishment of the capabil-

  ity team as being ‘totally political’. He sees ‘that villain Briggs’

  as creating many of the problems with the project, from his early

  involvement in drawing up the requirements to his later role in aid-

  ing and abetting John Moore’s attacks on the project. In his view

  most of the problems with the submarines were either already

  solved or well on their way to being fixed. However, Moore

  wanted to spend money on the submarines so that he could claim

  to have fixed them and Briggs was happy to take the money, even

  though the improvements he put on the submarines made only a

  marginal difference to their performance.

  In spite of his strong opposition to the process as an unnec-

  essary waste of money, Ohff ensured that ASC cooperated fully

  with Briggs’ capability team. Doug Callow recalls that after the

  company’s management had its first briefing from Briggs, ‘we all

  looked at Hans and thought, “How’s he going to take this?”’. But

  when Briggs left, Hans Ohff simply told his managers: ‘Do what

  he wants.’4

  ‘ T H A T V I L L A I N B R I G G S ’

  291

  The key requirements for the fast-track submarines were seen

  as being reliable diesels, a quieter hull shape, new propellers, a

  working combat system and new electronic surveillance equip-

  ment. Two other vital issues were the support structure for the sub-

  marines and the shortage of submariners. Peter Briggs called the

  manpower crisis ‘the big sleeper issue that McIntosh and Prescott

  had not identified’ and he emphasised that ‘none of the other issues

  were relevant unless the manpower problem was fixed’.

  All but the need for new electronic surveillance equipment and

  the manpower crisis had been identified in the McIntosh-Prescott

  report and other reports on the submarines, and in most cases the

  remedies had also been decided and were well under way. The

  contribution of Peter Briggs and his capability team was to kick

  heads, break down doors, ignore excuses, bully laggards and get

  results. Regardless of past bitterness, all the groups involved were

  made to work together to improve the submarines. The govern-

  ment had provided extra money so ‘there was a need to get people

  to stop arguing about the submarines and fix them’.

  Peter Briggs spent much time and energy dealing with the man-

  power crisis and forcing solutions through the system. Through

  measures such as giving priority to those volunteering to begin

  submarine training, forcing 20 per cent of qualified crews into

  shore billets to give relief from continual sea service, reducing the

  size of the trials crew at ASC, and introducing a large retention

  bonus, submariner numbers began to grow. By the end of 2000

  ‘qualified Collins manpower had increased from 37 per cent to 55

  per cent of the numbers required for six operational submarines’.5

  Progress on the mechanical improvements to the submarines

  was rapid ‘because the engineering staff in the project office

  already had developed design change specifications by the time

  they were needed for negotiations with ASC’. Many of the pro-

  posed changes had already been made on one or more of the sub-

  marines before McIntosh and Prescott reported and Peter Briggs

  was appointed.6 Consequently, the central issue was not deciding

  what needed to be done but reaching agreement with ASC and its

  sub-contractors on who should pay for the work, and ensuring

  that it was done promptly and without further dispute.

  The diesel engines suffered from numerous problems, which

  were mostly minor and fairly readily fixed, but the fact there were

  292

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  so many of them meant that the engines were inherently unreli-

  able and frequently disrupted the submarines’ trials and opera-

  tions. The final straw for many submariners was in 1998 when

  Farncomb had a horrific passage back from Timor with no diesels

  working and the crew living on orange juice and then spending sev-

  eral weeks stranded in Darwin waiting for spare parts. Nonethe-

  less, by the time ‘fast track’ started many of the minor problems

  had been resolved and the diesels were becoming more reliable.

  Possibly the most important action taken during the ‘fast-track’

  period was increasing the strength of the engine mounts to prevent

  twisting and distortion and reduce the excessive vibrations, which

  the DSTO experts had advised were behind many of the failures.

  Peter Briggs and his team fast-tra
cked the modifications to

  the casing designed by DSTO and the Americans to reduce flow

  noise. There is general agreement that these changes improved the

  noise signature of the submarines, although strong disagreement

  remains as to how significant the improvement was.7 The installa-

  tion of American-modified propellers was also fast-tracked, with

  similar disagreement on the significance of the changes.

  Peter Briggs accepted the McIntosh-Prescott recommendation

  that the combat system should be scrapped and the best ‘in-service’

  system should be bought for the Collins class. In his view the orig-

  inal Rockwell combat system (by early 2000 owned by Raytheon)

  ‘did not even provide a foundation for where we needed to go’.

  Consequently an agreement was reached with Raytheon to end

  the production of incremental improvements to the system, with

  the last ‘drop’ taking place early in 2000. The submarine capabil-

  ity team then began the process of choosing a new combat system

  but, since this would clearly not be completed in time to install

  it in the fast-track submarines, these were to be fitted with an

  ‘augmented’ combat system to bring them up to the required min-

  imum operational capability.

  The augmented combat system owed much to the contingency

  work already done by the project team and DSTO’s combat system

  research team, complemented by the SWSC and the US Navy. The

  process of adding ‘black boxes’ to the combat system was already

  under way and the capability team continued this process. The

  links between the new submarine project and the SWSC were

  renewed in the late 1990s, after the centre had been cut out of

  the project since the late 1980s when most of its senior staff left

  ‘ T H A T V I L L A I N B R I G G S ’

  293

  to join the companies involved in building the Rockwell system.

  The centre had quietly continued its work with the Oberons and

  responded with enthusiasm to assisting with the new submarines.

  The augmentation package was made up of commercial off-the-

  shelf consoles with equipment from the US Navy and Australian

  companies.

  Todd Mansell of DSTO remembers the rather informal circum-

  stances of the undertaking:

  Installation of the initial augmentation system was pretty

  hairy. ASC had utilised connectors for data cables that were

  done to military specifications but the computers used by

  NUWC were mostly commercial-off-the-shelf. When DSTO

  was called on by the project to ‘groom the combat system’

  prior to formal testing, we discovered that physical

  connection had been achieved by simply stripping the plugs

  and splicing the cables together with plenty of electrical tape.

  Ted Vanderhoek, who had been at SWSC and the submarine

  project before setting up a consultancy with former submariner

  Mike Gee, had studied ways to use commercial off-the-shelf equip-

  ment in an open system environment before becoming involved

  with the augmentation project. He recalls that:

  With fast track it was a matter of ‘here’s a bunch of stuff

  we’re going to put on the sub – make it work’. The project

  was working in shifting sands and at first we were told not to

  worry about the process – just get it happening by the

  deadline – but then we had to go back and fill the spaces to

  appease the regulators.

  There was a lot of politicking in fast track. It was an

  opportunity for Australian companies to get their products

  on the submarines . . . We were given all these products to

  put on board and some of them overlapped. No-one really

  knew what they wanted on the subs and they overdid it a bit

  in what they did put on. There was lots of political pressure

  to include the Australian systems and this led to overlaps

  with the American systems. To some extent it became a demo

  of the products at the expense of a concise system for the

  submarines. The augmented system has since been

  rationalised and the later submarines were more pragmatic.

  294

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  Although the augmented combat system reached the minimum

  operational requirements set for the acceptance of the submarines,

  it was still well short of the capability envisioned when the require-

  ments had been drawn up in the early 1980s. Peter Briggs agrees

  that the augmented combat system was probably not as good as

  the Oberons’ combat system. He says: ‘A submarine on submarine

  fight is like a knife fight in a dark alley and in an Oberon versus

  [fast-tracked] Collins fight, the Oberon might well win.’

  One issue dealt with by the capability team that had not

  been discussed in the McIntosh-Prescott report was the electronic

  surveillance equipment on the submarines, which is vital for the

  work done by Australian submarines. The equipment for the

  Collins class had been state of the art when it was purchased

  but was obsolete and inadequate by the late 1990s. Six sets of

  equipment had been bought in the 1980s but the sets for the last

  three submarines ‘didn’t get out of their boxes’. The submarine

  project team bought, installed and tested new equipment, initially

  in the two fast-track submarines and then in the other four.

  The issue of the electronic surveillance equipment highlights

  one of the central features of the fast-track project. In the eyes of

  the public and the politicians the aim of fast track was to fix the

  ‘dud subs’ but in fact more time and money was spent upgrading

  the technology on the submarines than fixing faults. Peter Briggs

  analysed the position:

  Operational growth from the fixed price, minimal

  contingency contract over 12 years was the biggest source of

  issues. The strategy of no prototype, no technology insertion

  and no revision of operational requirements led to a backlog

  of issues. The notion that you froze the contract, you froze

  the requirements and you kept the operators the hell away

  from it so you didn’t get any change orders – the chickens

  came home to roost when the operators said ‘bloody thing

  doesn’t do what we want it to do’. The operators were not

  involved from 1987 to 1999 and things changed over that

  time.

  An important step forward came when Peter Briggs and Hans

  Ohff agreed to assess the work that needed to be done, and divide

  the issues into black, white and grey: black where the contract

  specifications had not been met and ASC was responsible for

  fixing the problem; grey where there was mixed responsibility

  ‘ T H A T V I L L A I N B R I G G S ’

  295

  or where responsibility could not be agreed on; and white where

  the requirement had changed or the specified technology was out

  of date and the Commonwealth was responsible. In August 1999

  there were 120 issues, of which 28 were rated as black, 61 as

  white, 20 as grey and 11 were uncategorised – more than half the

  issues were accepted as
being the Commonwealth’s responsibility.

  Lawyers Paul Armarego and Wal Jurkiewicz suggested the

  approach the capability team followed in negotiating the

  fast-track changes. They analysed the position:

  Looking back at the contract, one of the main problems was

  that the specifications were 1987 specifications and they were

  trying to get them to fit the situation in 2001. The only

  obligation ASC had was in terms of the 1987 specifications

  and the only chance the Commonwealth had of enforcing

  them was in terms of the 1987 specifications. Yet by 2001

  some of the original suppliers were no longer in business and

  many of them no longer made the equipment that was being

  complained of in 2001. Yet by 2001 the navy wanted 2001

  standards, not 1987 standards so we suggested that ASC

  should pay to get the submarines to the level of the 1987

  specifications as set out in the contract and the

  Commonwealth should pay the extra required to get them up

  to 2001 standards. ASC would do the work and the

  Commonwealth would pay the difference.8

  In early June 2000 the submarine project office prepared this

  report as a potential press release:

  Aloha HMAS Waller – Australia’s submarine

  success!

  As part of her longest overseas operational deployment, the

  Royal Australian Navy’s (RAN) Collins-Class submarine

  HMAS Waller has played a significant role in the highly

  successful anti-submarine warfare exercise conducted

  27–30 May 2000. During the recent exercise HMAS Waller

  became the first RAN submarine to be fully integrated and

  work in direct support for an USN Carrier Battle Group

  [CVBG] . . .

  296

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  Throughout the exercise, HMAS Waller’s mission was to

  search and locate an opposing submarine, and provide

  reports to the CVBG. The opposing force was successfully

  tracked, targeted and attacked by the Australian submarine

  on a number of occasions. The Royal Australian Navy’s

  submarine crew provided timely intelligence to enable the

  CVBG to alter its course through a narrow sea passage and

  avoid the opposing submarine threat. The Australian

  Collins-Class submarine’s successful involvement ensured the

  CVBG came through the recent exercise unscathed . . .

 

‹ Prev