  The contact center is built up, and the services for

  diff

  fferent ministries are implemented.

  2010 and 2011

  The HR service level quality is maintained, and the

  services for the other ministries are implemented,

  providing the total HR service delivery to the

  majority of ministries.

  Source: Lievense, 2005; P-Direkt, 2002; 2003; 2004a; 2004b; 2005a; 2005b; 2007; 2008; 2011.

  5 ANALYSIS AND DISCUSSION

  5.1 Phase I: Initiation of P-Direkt and Its Initial Failure

  A key aspect of defi

  fining a new HRM system was to increase the effi

  c

  ffi iency and

  quality of the HR function of the diff e

  ff rent individual ministries by bundling

  these activities into one central entity that could provide HR services to the

  central government. The government therefore decided to implement an SSC

  to both benefi t f

  fi rom economies of scale as well as increase the service quality,

  as scarce HR expertise could then be shared among the ministries. When the

  decision would have to be made, certain actions needed to have been com-

  pleted. This was however not the case. The division of responsibilities was still

  insuffi

  c

  ffi iently defi

  fined and moreover, no arrangements were made regarding the

  way P-Direkt would have to be managed during the period it would be opera-

  tional. The business case was unclear and not convincing in terms of realizing

  the expected effi

  c

  ffi iency gains, reduction of personnel costs and of bureaucracy

  (P-Direkt, 2005b). Still, because of political pressure to quickly get results, the

  government decided to go ahead with the implementation.

  In July 2003, there is fi

  final green light for the realization of the HRM SSC

  that should be operational on January 1, 2006. The scope of the HRM SSC

  would initially consist of the following activities: salary administration; person-

  nel contract administration, annual and sick leave registration; other fi

  financial

  staff com

  ff

  pensation, e.g. expenses and data about the department and internal

  organization (P-Direkt, 2003; 2004a; 2004b). It is decided that the design,

  E-Government Implementation in Times of Change 217

  implementation, and maintenance of the ICT infrastructure for the SSC will

  be outsourced to a third party and the most important reason to do so, was

  that the government wanted to use the market’s best practices and common

  uniform standards. Moreover, the government wanted to have the third party

  pay for the design costs in exchange for a multi-year contract to maintain the

  system. It can be questioned whether this was a good strategy, as it created a

  signifi c

  fi ant dependency on an external party. After a European tender process,

  a consortium of two IT providers was selected and an outsourcing contract

  was signed. During the negotiations, it was decided that there was not enough

  time to defi

  fine the product specifi ca

  fi tions and acceptance criteria and this would

  therefore all be done in a next phase, which was not a proper basis to start the

  realization phase (P-Direkt, 2005a; 2005b). Payment to the consortium was

  based on the realization of milestones, but given that there were no accep-

  tance criteria defi

  fined for these milestones, the government was not able to take

  proper legal measures when the consortium did not meet their expectations.

  The contract did not take this aspect into account, and the signed contract

  was not reviewed by an independent third party law fi

  firm (P-Direkt, 2007).

  Some critical remarks by other third-party consultancy fi

  firms about the risks

  were ignored and in that regard the risk management and quality assurance

  processes were not properly part of a formal governance process.

  The architectural design created by the consortium for the ICT infra-

  structure was not approved by the government on two consecutive occa-

  sions because it didn’t meet their expectations, and the consortium decided

  to retract itself from this process as no agreement could be made about the

  next steps. The state was obliged to pay 20.8 million euro compensation,

  mainly for retaining the right to interim products, licenses, and documen-

  tation that could later still be used. At the end of 2005, the Minister respon-

  sible for this project confi rm

  fi

  ed that he still wanted to go forward with the

  SSC and demanded an investigation into why the project failed.

  There were many lessons learned and a variety of shortcomings in the

  decision-making process. The strategy, the management and control on the

  part of the government were contributory factors in the failure of the tender-

  ing and implementation process. On a number of crucial occasions, decisions

  were taken under excessive time pressure, and as such the decision process

  did not meet the quality demands of the central government, also because

  insuffi

  c

  ffi ient account was taken of the criticism from diff eren

  ff

  t external experts

  about the management of the tendering process. Unsolved issues with the con-

  sortium were put off

  ff until a subsequent phase, including agreements about

  the expected performance and acceptance criteria by which this performance

  could be assessed (P-Direkt, 2007). Moreover, the information given about

  the progress of the SSC was often too optimistic. Working together with a

  private party consortium required a professional government commissioning

  practice, but this was not the case, and there was no adequate project manage-

  ment. There was insuffi

  c

  ffi ient quality assurance and risk management of the

  products or services and insuffi

  c

  ffi ient information provision to all the stake-

  holders involved. Moreover the expectations with respect to the timeline of

  218 Anton

  Joha and Marijn Janssen

  the project and its milestones were not properly managed and not enough sup-

  port was created among the most important internal and external stakeholders

  (P-Direkt, 2005b).

  There were dependencies of P-Direkt with other HR projects that were

  managed outside the formal responsibility of P-Direkt, though they were

  important elements within the new HRM system. This implied that P-Direkt

  was not able to adjust certain aspects of their project but had to escalate this to

  the responsible people within the other projects. This layered project manage-

  ment approach was causing ineffici

  ffi encies (P-Direkt, 2007). Moreover, because

  the dependencies with certain projects were critical and these projects were

  not able to meet their planning, the planning for P-Direkt regarding which

  services should be operational at a certain date also needed to be changed.

  Coordination requires good communication about the progress of each of the

  projec
ts and the use of quality management tools, which was not the case.

  There was no unifi e

  fi d overall vision of quality management, which there-

  fore did not result in a consistent and coherent quality management process

  (P-Direkt, 2007). P-Direkt’s cost savings were partially based on the assump-

  tion that the ministries did not have to have any HR activities anymore at all,

  but P-Direkt was not able to provide the ministries with the dates that they

  could discontinue their services and fully rely on the services provided by

  P-Direkt. The ministry of fi

  finance had already started their own HR project,

  and moreover, there was a far longer period where both P-Direkt as well as the

  individual ministries executed several complementary HR activities (Lievense,

  2005). In Table 16.2, the lessons learned have been summarized using Baldwin et al.’s (2001) four dimensions.

  Table 16.2 Lessons Learned from the P-Direkt Case Study

  Dimension

  Lessons learned

  • The (master) planning was too ambitious

  • Too many things were tried to be changed at the same time

  • Role of the project principal was too weak

  • Improve internal communication as the individual ministries were

  not able to keep up with the decision speed

  Strategic

  • Project management tools were either not available or still in

  and

  development

  organiza-

  • Knowledge was too dependent on too many external people

  tional

  • Too many project leaders making it unclear who is responsible and

  accountable

  • The project management governance was not the same for the dif-

  ferent individual sub-projects and for the different m

  ff

  inistries

  • Either no clear responsibilities (and accountabilities) or the wrong

  responsibilities were assigned to diff erent parties involved

  ff

  (continued)

  E-Government Implementation in Times of Change 219

  Table 16.2 (continued)

  Dimension

  Lessons learned

  • The HR department was not enough involved, and the project

  therefore lacked HR experts able to properly review the proposed

  ideas and solutions

  Strategic

  • Unclear governance model and no clear alignment between the stra-

  and

  tegic, tactical and operational levels across the diffe

  ff rent ministries

  organiza-

  • There was no experience with performance-based contracting

  tional

  • Division of responsibilities between the stakeholders involved was

  (continued)

  insuffi

  ciently

  ffi

  defin

  fi ed

  • There was unclarity about the way the service delivery model and

  the way the services were going to be provided to the organization

  • Insuffi

  cient attention for the users and change management was given

  ffi

  • No integral and consistent project management approach and

  methodology

  • Due to too much political pressure and ambition, reports were too

  optimistic and positive about the project benefi ts and the progress

  fi

  made during the project preparation phase

  • The third parties involved were not able to provide relevant input

  as the design choices were already made

  • Before any key project decision could be taken, a number of condi-

  Political

  tions had to be satisfi ed that the government had defi

  fi

  ned already

  fi

  in advance

  • Ensure an open relationship with the external service provider and

  enough countervailing power between all parties when using a

  performance-based contract.

  • More communicating about the relevance and necessity of the new

  project to the internal organization to get more understanding and

  support

  • Share relevant knowledge with third parties as these were not up

  to date about certain (legal) project requirements

  • Overestimation of the possibilities of ICT

  • Consolidation and standardization eff orts of the diff

  ff

  erent

  ff

  ICT

  systems across the ministries had not taken place

  • Acceptance criteria, interfaces and technical standards were not

  Technical

  clearly define

  fi d

  • Dogmatically trying to keep the scope the same as it was initially

  agreed on, resulting in less effi

  ciently working processes when

  ffi

  these are separated in an illogical and unnatural way

  • The business case was ambiguous and not convincing

  • No regular check and update of the business case was performed

  Economic

  • Unclarity about the funding model and the costs for the ministries

  • Bonus constructions need to part of a performance-based contract

  with a third party to ensure that the third party is incentivized to

  use innovative tools, methods and quality checks

  220 Anton Joha and Marijn Janssen

  5.2 Phase II: Redesign and Re-initiation of P-Direkt

  Based on the lessons learned, a new project approach was defined (P-Direkt,

  2008; 2011). An important change in the strategy was to have a more phased

  approach of the project using a growth model and a realistic planning. Three

  stages were defined, and in the fi

  first stage there was a focus on simplifying,

  digitalizing, and bundling the HRM activities within each of the individual

  ministries, with the main purpose to come to one ICT standard for the sal-

  ary administration. Moreover, several ministries had to implement a self-ser-

  vice concept and helpdesks. The ministries themselves were responsible for

  the implementation and received support from P-Direkt. This fi

  first stage was

  planned to take 1 to 2 years, and this went according to plan. In 2008, twenty-

  six standard HRM-processes were defi

  fined for the central government, there

  was a self-service portal for the diff eren

  ff

  t ministries and a central digital per-

  sonnel dossier service, and the civil servants of a number of ministries were

  getting paid via P-Direkt (Annual Report P-Direkt, 2007; 2008). At this stage

  the diff eren

  ff

  t ministries were able to choose out of diff eren

  ff

  t temporary scenar-

  ios to connect to P-Direkt, depending on how much progress they had made

  and what salary administration system they used.

  The second stage started in 2009 and was to implement one HRM admin-

  istration and contact center for all participating ministries. This included

  the physical migration of personnel to a limited number of SSC locations.

  The activities of P-Direkt were performed by four main departments, includ-

  ing a development department where services are developed and a services

  delivery systems department where the services are managed and maintained

  after developm
ent. Moreover there is a P-services department responsible

  Table 16.3 Main Characteristics of the New Project Approach after the

  Re-initiation of P-Direkt

  Dimension

  Main characteristics of the new project plan and methodology

  • Using an incremental growth model and defi ning projects

  fi

  with few mutual dependencies

  • Realistic master planning

  • Better usage of existing HR knowledge, experience and people

  Strategic and

  • Introducing uniform HR processes across all participating

  organizational

  ministries

  • New governance model

  • Professional project and program management

  • Introducing an implementation of a support helpdesk

  Political

  • Attention for change management

  • Connecting to the demands of each of the diffe

  ff rent ministries

  Technical

  • Use of technical standards and interfaces, so that each minis-

  try could connect to P-Direkt

  Economic

  • New funding model and clarity about who is paying what

  E-Government Implementation in Times of Change 221

  for the non-automated services of P-Direkt that includes the helpdesk, and

  fi

  finally there is a department for simplifying and unifying processes, taking

  into account the legal and regulatory requirements (Annual Report P-Direkt,

  2009; 2010). Table 16.3 provides the main characteristics of the new project plan and methodology (P-Direkt, 2008; 2011).

  6 CONCLUSION

  Shared service centers provide a solution for public sector organizations

  that lack resources and want to reduce costs and increase service levels at

  the same time. The implementation of a large-scale SSC with many differ-

  ent stakeholders is a complex transformation project. In this chapter we

  explored the largest Dutch governmental HR SSC addressing the whole

  government in the Netherlands that initially failed and only became suc-

  cessful after redefi

  fining the scope, governance, and implementation strategy.

  We identifi

  fied the lessons learned from a organizational, strategic, political,

  economic, and technical perspective and also identifi

  fied the main changes

  that have been made when the SSC was re-initiated.

  Already before the decision was made to implement the SSC, a number

  of critical actions were not fi

  finalized. During the implementation phase

  itself, there were many lessons learned. These include a realistic master

 