Book Read Free

Renovation 4th Edition

Page 57

by Michael Litchfield


  zzzzzz Joists perpendicular to a Foundation Wall

  2 ft. or less

  Joists

  Pony wall

  Support beam

  Jack

  Mudsill

  Cribbing

  Foundation

  Supporting the structure: When joists

  run perpendicular to the foundation

  wall you’re working on, support their

  load with a beam parallel to the wall.

  To determine the height of the shoring posts, jack the beam

  Al owing yourself room to work, put this

  to the desired height, level the footing block, and measure

  beam as close to the wall as possible—

  between the two. Nail the post cap on before inserting the

  in most cases, 2 ft. is optimal.

  post. Because this needle beam is simply holding a wall in

  place—not raising it—it was jacked just snug to a wall plate.

  3. Positioning a jacking beam requires prep

  mine the height(s) of the shoring posts. (If you

  work. Ideally, the crew should raise the beam

  jack up an additional 1⁄8 in., you’ll find it easier to

  into place and then immediately plumb and set

  slide shoring posts in.)

  the jacks. But they may need to catch their

  5. After you’re done jacking, install the shoring

  breath or gather equipment before setting the

  posts, which are more stable than jacks on posts.

  jacking posts. In that event, cut two 2x4s approxi- To keep the shoring posts in place, nail steel caps

  P R O T I P

  mately 1⁄2 in. longer than the distance from the

  to their tops before installing them. Once you’ve

  underside of the beam to the top of the cribbing

  placed the posts under the footing beams, attach

  if a new foundation section

  plates, and use a sledgehammer to wedge a

  the post caps to the beams, and add cross brac-

  isn’t terribly long or deep, use an

  2x4 under each end of the beam. Caution: This

  ing or plywood gussets to keep the beam from

  electric demolition hammer with

  setup is inherently unstable, so workers should

  a shovel bit to excavate the

  rotating. Once you’ve plumbed the shoring posts

  monitor both 2x4s continually to make sure they

  trench. this tool is particularly

  and braced the beams, lower the jacks slowly

  don’t kick out.

  helpful when there’s no room

  until they no longer bear weight, and then remove

  to swing a pick. shovel bits

  4. As soon as the beam is in place, cut posts

  them. With shoring supporting all necessary

  cut a clean edge and dig them-

  10 in. shorter than the distance from the under-

  bearing members, you’re ready to begin repairs.

  selves in, even in heavy clay.

  side of the beam to the top of the footing blocks.

  Note: Some foundation contractors install two

  then you simply shovel out the

  This 10 in. is roughly the (closed) height of a

  shoring posts—one on either side of the jacking

  loosened soil.

  hydraulic jack plus a little room to move. With a

  post—for greater stability. Once the jack is

  helper, place jacks and posts under both ends of

  removed, nail two 3-ft.-long 2x4 diagonal braces

  the beam, plumb the posts, and start jacking.

  between the two shoring posts; for this, use a

  Center each jack on its footing blocks so there’s

  pneumatic nailer. Hammer blows could dislodge

  plenty of room for the shoring post(s) that will

  the posts.

  follow shortly. (If you use hydraulic jacks, you

  6. When your repairs are finished, begin to

  can position the shoring posts 3 in. to 4 in. from

  remove the shoring by reinserting the jacks and

  the jacking posts.) As you jack, try to raise both

  then simultaneously raising all the jacks slowly

  ends of the beam evenly, using a 4-ft. or 6-ft. spirit and evenly to take weight off the shoring. Leave

  level to check for level.

  the cross bracing in place until those loads are

  When the beam is at the desired height, mea-

  removed. Then, keeping the jacking posts plumb,

  sure down to the tops of footing blocks to deter-

  carefully remove the post-and-beam bracing and

  242 Chapter 10

  lower and remove those elements. Gradually

  and jack just enough to take the load off the post—

  lower the building onto its new pads, posts, and

  plus 1⁄8 in. Remove the rotted post, measure from

  foundation, then remove the jacks.

  the underside of the girder to the pad (remem-

  bering to subtract the 1⁄8 in.), and cut a new

  post—preferably from pressure-treated lumber.

  Minor Repairs and Upgrades

  To keep this new post from rotting, cut a

  The category minor repairs includes anything

  22-ga. sheet aluminum plate and place it under

  short of replacing a failed foundation, which is

  the bottom of the post. A dab of silicone caulking

  covered in the next section. Repairing surface

  will hold it in place while you plumb and posi-

  cracks is explained on p. 237.

  tion the post, then lower the jack so the new post

  bears the load. Or replace the wooden post with a

  replaCing posts and pads

  preprimed metal column. However, if basement

  If floors slope down to a single point, there’s a

  floors are wet periodically—suggested by sedi-

  good chance that a post or pad has failed. If a

  ment lines along the base of the walls—build up

  floor slopes down to an imaginary line running

  or replace the existing pad with a taller one to

  down the middle of the house, there’s probably a

  elevate the base of the post. Add a sump pump,

  girder sagging because of multiple post or pad

  too, as explained on p. 258.

  failures. Fortunately, the cures for both condi-

  replacing pads. Replace concrete pads that

  tions are relatively straightforward.

  are tilting or sinking because they are too small

  Post repairs. The most common cause of wood-

  for the loads they bear. Likewise, you’ll need to

  en post failure is moisture wicking up through a

  pour a new pad if there was no pad originally

  concrete pad, rotting the bottom of the post. To

  and an overloaded post punched through the

  replace a damaged post, use the techniques just

  concrete floor. Pads for load-bearing columns

  described in “Jacking and Shoring.” Place footing should always be separated from floors by

  blocks as close as possible to the existing pad,

  isolation joints.

  Cutting into a Concrete Floor

  to enlarge an existing load-bearing pad or create a new one, you

  thick and reinforced with rebar, you can spend a day accomplishing

  may need to cut through a concrete floor. depending on the condition

  very little. Well . . . you get the picture.

  and thickness of that floor, the job will range from nasty to horrible.

  Fortunately, for a few hundred bucks you can hire a concr
ete-cutting

  Cutting concrete is noisy, dirty, and dangerous, and the tools are

  subcontractor to cut out a pad opening in about an hour. (don’t forget

  heavy and unpredictable. Wear safety glasses, gloves, hearing pro-

  to allow for the thickness of the formboards when sizing the opening.)

  tectors, and a respirator mask. adequate ventilation and lighting

  the subcontractor also can bore holes needed for drainpipes and such.

  are a must.

  if the floor was poured before the 1950s, you’ll likely find that it is

  only 3 in. to 4 in. thick and is without steel reinforce-

  ment. the floor also may be badly cracked. in this

  case, you can probably break through it with a pickax,

  but to minimize floor patching later, rent an electric

  concrete-cutting saw with a diamond blade to score

  around the opening. then finish the cut (the saw-

  blade rarely cuts all the way through) with a hand

  sledge and a chisel.

  Be advised, however, that a concrete-cutting saw

  cuts dry and thus throws up an extraordinary amount

  of dust. therefore, you may need to seal off the base-

  ment with plastic barriers and then spend an hour

  vacuuming afterward. alternatively, you can rent a

  gasoline-powered wet-cut saw, which keeps down the

  A gasoline-powered, wet-cut saw has a diamond blade and is connected to a water

  dust but fills the basement with exhaust fumes. and,

  supply (via the yellow fitting), which reduces airborne dust when cutting concrete.

  if the concrete floor is a modern slab that is 5 in.

  Foundations and Concrete

  243

  If your floors are springy and joists exceed the

  joiSt SizE

  tyPiCAL SPAN (ft.)

  following rule-of-thumb lengths, consider adding

  26

  

  8

  a girder.

  An engineer can size the girder for you. “Beam

  28

  

  10

  Span Comparison” below shows maximum spans

  210

  

  12

  for built-up girders in two-story houses.

  Ideally, the new girder should run beneath the

  212

  

  14

  midpoint of the joist span, but if existing ducts or

  drainpipes obstruct that route, shift the girder

  location a foot or two. Once you locate the girder,

  snap a chalkline to mark its center, and plumb

  Load-bearing pads should be 24 in. by 24 in.

  down from that to mark positions for pads and

  by 12 in. deep, reinforced with a single layer of

  posts. Place posts at each end of the girder and

  No. 4 (1⁄2-in.) rebar arranged in a grid. Pads sup-

  approximately every 6 ft. along its length. If you

  porting a greater load (such as a two-story house) create a girder by laminating several 2xs, keep at

  should be 30 in. by 30 in. by 18 in. deep, with

  least one member of the “beam sandwich” con-

  two layers of No. 4 rebar; in each layer, run three

  tinuous over each post.

  P R O T I P

  pieces of rebar perpendicular to three other

  Size and reinforce pads as described in the

  pieces. In either configuration, keep the rebar

  preceding section. After the concrete pad has

  Before adding a girder to cor-

  back 3 in. from the edges of the pad.

  cured for a week, bring in the girder or laminate

  rect springy floors, go under the

  Line the forms with sheet plastic so that the

  it on site from 2-in. stock. Prescribed widths

  house and see if there’s solid

  water in the concrete won’t drain into the soil

  for built-up girders are usually three 2x boards

  blocking or cross bridging

  and weaken the pad. (Plastic also prevents soil

  (41⁄2 in. thick when nailed together). For built-up

  between joists. if not, add it,

  moisture from later migrating through the pad

  girders and beams, the Uniform Building Code

  and that may be all you’ll have to

  and rotting the post.) If you carefully level the

  do to stiffen the floors. if floors

  recommends the following nailing schedule:

  tops of the formboards and screed off the con-

  sag between joists, the subfloor-

  20d nails at 32 in. on center at the top and bottom

  ing may be too thin.

  crete to them, the top of the pad will be level as

  and two 20d nails staggered at the ends and at

  well. Allow the concrete to cure before putting

  each splice.

  weight on it: three days minimum but seven days

  Whether solid or laminated, if the girder has a

  recommended.

  crown, install it so it faces up. Installing a new

  girder is essentially the same as positioning a

  adding a girder

  temporary shoring beam, except that the girder

  will stay in place. Have helpers to raise the girder

  Adding a girder under a run of joists shortens the and support it until permanent support posts are

  distance they span, stiffens a springy floor, and

  in place. Properly sized, the pad will have more

  reduces some loading on perimeter foundations.

  zzzzzz Beam span Comparison

  Beam span Comparison

  Typical

  joiSt SPAN (x/2 + y/2)

  joist

  Header or

  other support

  8 Ft.

  10 Ft.

  12 Ft. 14 Ft.

  Beam

  BEAM tyPE

  BEAM SPAN (ft)

  (2) 2x8 built-up beam

  

  6.8

  6.1

  5.3

  4.7

  4x8 timber

  

  7.7

  6.9

  6.0

  5.3

  y/2

  y/2

  Joist

  31⁄8-in. x 71⁄2-in.

  Header

  x/2

  span y

  glue-laminated beam

  

  9.7

  9.0

  8.3

  7.7

  x/2

  Use this drawing and table for

  Beam

  estimating beam sizes and

  supports

  31⁄2-in. x 71⁄2-in. PSL beam

  

  9.7

  9.0

  8.5

  8.0

  1

  comparing beam types for

  /2 of each

  joist span, or

  (2) 13⁄4-in. x 71⁄2-in.

  uniform floor loads of a 40-psf

  Joist

  x/2 + y/2. See

  span x

  LVL (unusual depth)

  

  10.0

  9.3

  8.8

  8.3

  (pounds per square foot) live

  table at right.

  load and a 15-psf dead load.

  Header

  4x8 steel beam

  Have a structural engineer

  supports

  (W8 x 13 A36)

  

  17.4

  16.2

  15.2

  14.1

  calculate your actual loads.

  1/2 of single

  joist span.

  244 Cha
pter 10

  replacing a Wooden girder with an i-Beam

  as level building lots continue to disappear, we’ll need to make the

  most of sites once thought unbuildable, such as the remodel in the

  photos here, which takes place on a steep, south-facing slope above

  san Francisco. the lot’s high side bordered a city street, so a garage

  right on the street became the portal to descending stairs, an elevat-

  ed walkway, and a dramatic, modern house set downhill about 50 ft.

  from the road.

  in time, the homeowner realized that the cavernous space under

  the garage could accommodate an in-law suite, so he hired stephen

  shoup, principal of Building lab in emeryville, Calif., to design and

  build it. the great challenge of the project involved transferring the

  loads borne by the main girder—which supported a garage floor

  above—to a steel i-beam set flush to the finished ceiling that would

  span the 22-ft. width of the suite without intervening support posts.

  the weights were considerable. the garage floor system consisted

  of 2x12 douglas fir joists spaced 12 in. on center, a 3⁄4-in. plywood

  subfloor, and a 4-in.-thick reinforced concrete slab. the clearances

  Unfinished space under the garage. The 6x12

  were also quite tight when it came time to cut through the garage

  Douglas fir girder, at top, spanned 22 ft. with

  the aid of 2x6 beam pockets at both ends and a

  floor joists: the slot cut was roughly 3⁄16 in. wider than the width of

  6x6 post at midspan. The white sticks about

  the i-beam—allowing 1⁄16 in. on each side of the i-beam and 1⁄16 in.

  halfway up the wall indicate the height of the

  of “wiggle room.” the fit had to be that exacting so joist ends could

  subfloor to come.

  be hung off the 2x12s bolted to the sides of the i-beam.

  you can see the finished suite on pp. 38–39.

  An I-beam on the way up.

  The subfloor in place, with an I-beam

  At left, shoring; upper

  waiting to be hoisted. Note that a slot

  right, a rectangular hole

  has been cut into the 2x12 ceiling-

  into which the beam end

  joist array above, into which the

  will fit once it has been

  W12x26 I-beam will fit. At this

  fully raised. At either end,

  transitional point, the girder and post

  posts will be cut to exact

  seen in the photo above right are now

  length, set into the wall,

  carrying roughly half the load—the

  and bolted to the legs of

  joists at left—and shoring, at right,

  the I-beam cap, which is

  supports the cut-through joists. Once

  an integrally welded

  the I-beam is in place, the severed

 

‹ Prev